PHASE 01: DEVELOPMENT
Progress on Ground
Tracking construction activities, milestones and structural development across the project corridor.
Progress Dashboard
Construction is progressing across the corridor, with focus on earthwork, road development and structural works.

MILESTONE I
180 DAYS
20%
MILESTONE II
35%
360 DAYS
MILESTONE III
75%
540 DAYS
COMPLETION
730 DAYS
100%

Project Milestones
PROVISIONAL APPOINTED DATE
07 MAR 2026
03 SEP 2026
MILESTONE I — 20%
MILESTONE II — 35%
02 DEC 2026
29 AUG 2027
MILESTONE III — 75%
PROJECT COMPLETION — 100%
06 MAR 2028
Construction Progress
EARTHWORK
23.505 km Scope
7.57 km WIP
SERVICE ROAD
1.75 km
Infrastructure Scope
LOOPS & RAMPS
8.250 km
Connecting Roads

Building the Infrastructure Beneath and Above the Highway
170
Total Structures
73
Box Culverts
32
Mini Underpasses
25
Pipe Culverts
11
Vehicular Underpasses
8
Light Vehicular Underpasses
5
Small Vehicular Underpasses – MCW
4
Minor Bridge Cum Underpasses
3
Major Bridge Cum Underpasses
3
Flyovers
1
ROB
1
Vehicular Overpass

Progress Through Every Stage
Planning
Earthwork
Structures
Roads
Completion
Monthly Progress Update